Last reviewed: November 2, 2026. Formulas checked against standard industry conversions. How we calculate.
To estimate concrete yards, multiply the length × width × thickness in feet to get cubic feet, then divide by 27 to convert to cubic yards. Add about 5 to 10 percent for waste and uneven ground. For example, a 10 ft × 10 ft slab that is 4 inches thick needs about 1.23 cubic yards, or roughly 1.35 cubic yards with a 10 percent allowance.
This guide shows how to figure out yards of concrete needed for slabs, patios, driveways, footings and columns, how many 80 lb and 60 lb bags make a yard, how much one bag covers, and how ready-mix and bagged concrete compare.
Bag yields vary by brand, so check the label. These are planning estimates, not guarantees.
Concrete yardage estimator
Enter your slab size to see cubic yards and bags. Results update as you type.
Assumes 0.6 ft³ per 80 lb bag, 0.45 ft³ per 60 lb bag and about 4,000 lb per cubic yard. Confirm yields and quantities with your supplier.
How to Estimate Concrete Yards: The Formula
Concrete is sold by the cubic yard. A cubic yard is a volume of 27 cubic feet (3 ft × 3 ft × 3 ft). To calculate how much concrete you need, find the volume of the space to fill and convert it to cubic yards.
- Convert thickness to feetThickness in inches ÷ 12 = Thickness in feet
- Calculate cubic feetLength (ft) × Width (ft) × Thickness (ft) = Cubic feet
- Convert to cubic yardsCubic feet ÷ 27 = Cubic yards
- Add a waste allowanceCubic yards × 1.05 to 1.10 = Cubic yards to order
Use the same units throughout. If you measure in inches or meters, convert to feet first, or divide inches by 12 as shown above.
How to Measure for Yards of Concrete
- Measure length and widthAlong the inside of the forms, in feet
- Decide the thicknessSlabs and patios are commonly 4 in; driveways often 4–6 in. Follow local requirements.
- Split irregular shapesCalculate each rectangle separately and add the volumes
- Handle thickened edges and footingsCalculate them as separate, deeper sections
- Check the subgradeLow spots and uneven ground take more concrete
- Add a waste allowanceA 5 to 10 percent buffer avoids running short mid-pour
Example: How to Figure Out Yards of Concrete Needed
- Thickness: 4 ÷ 12 = 0.333 feet
- Volume: 10 × 10 × 0.333 = 33.3 cubic feet
- Cubic yards: 33.3 ÷ 27 = 1.23 cubic yards
- With 10 percent allowance: 1.23 × 1.10 = about 1.36 cubic yards
- In 80 lb bags: 33.3 ÷ 0.6 = about 56 bags (before allowance)
- Area: 12 × 12 = 144 square feet
- Volume: 144 × 0.333 = 48 cubic feet
- Cubic yards: 48 ÷ 27 = 1.78 cubic yards
- With 10 percent allowance: about 1.96, so order roughly 2 cubic yards
- In 80 lb bags: 48 ÷ 0.6 = 80 bags (before allowance)
- Area: 40 × 12 = 480 square feet; thickness 5 ÷ 12 = 0.417 feet
- Volume: 480 × 0.417 = 200 cubic feet
- Cubic yards: 200 ÷ 27 = 7.41 cubic yards
- With 10 percent allowance: about 8.15, so order roughly 8 to 8.5 cubic yards
A project this size is usually delivered by a ready-mix truck rather than mixed from bags. The next sections show how the numbers compare.
How Much Does 1 Cubic Yard of Concrete Cover?
Divide 324 by the thickness in inches to find the square feet that one cubic yard covers. This is the quick way to check an estimate or compare slab thicknesses.
| Slab thickness | Area covered by 1 cubic yard | Relative coverage |
|---|---|---|
| 3 inches | 108 square feet | |
| 4 inches | 81 square feet | |
| 5 inches | 65 square feet | |
| 6 inches | 54 square feet | |
| 8 inches | 41 square feet |
To use this chart, divide your area by the coverage figure. For example, a 200 square foot slab at 4 inches needs about 200 ÷ 81 = 2.47 cubic yards.
How Many Bags of Concrete Make a Yard?
A cubic yard has 27 cubic feet. Divide 27 by the cubic feet each bag yields to find the number of bags per yard. The yields below are typical for bagged concrete mix, but they differ by brand, so read the label.
| Bag size | Typical yield | Bags per cubic yard | Relative count |
|---|---|---|---|
| 40 lb | about 0.30 cubic feet | about 90 bags | |
| 50 lb | about 0.375 cubic feet | about 72 bags | |
| 60 lb | about 0.45 cubic feet | about 60 bags | |
| 80 lb | about 0.60 cubic feet | about 45 bags |
How many 80 lb bags of concrete in a yard?
About 45 bags. An 80 lb bag of concrete mix typically yields about 0.6 cubic feet, so 27 ÷ 0.6 = 45. If you are asking how many cubic feet are in an 80 lb bag of concrete, the answer is roughly 0.6 cubic feet.
How many 60 lb bags of concrete in a yard?
About 60 bags, because a 60 lb bag typically yields about 0.45 cubic feet (27 ÷ 0.45 = 60).
Bags needed by volume
| Cubic yards | 80 lb bags | 60 lb bags |
|---|---|---|
| 0.25 | 12 bags | 15 bags |
| 0.5 | 23 bags | 30 bags |
| 1 | 45 bags | 60 bags |
| 1.5 | 68 bags | 90 bags |
| 2 | 90 bags | 120 bags |
How many 80 lb bags of concrete are on a pallet?
Pallet counts vary by brand and store, but a pallet of 80 lb bags commonly holds around 40 to 45 bags, with 42 a common figure. At about 0.6 cubic feet per bag, that is roughly 24 to 27 cubic feet, or about 0.9 to 1 cubic yard of concrete. Confirm the count with the retailer before you order.
How much does one bag of concrete cover?
An 80 lb bag yielding about 0.6 cubic feet covers roughly 1.8 square feet at 4 inches thick (0.6 ÷ 0.333), or about 1.2 square feet at 6 inches. A 60 lb bag yielding about 0.45 cubic feet covers roughly 1.35 square feet at 4 inches.
How heavy is a yard of concrete?
A cubic yard of ready-mixed concrete weighs about 4,000 pounds. That is why concrete, like gravel, is easy to underestimate for hauling. For comparison, see how much a yard of pea gravel weighs.
Square Yards vs. Cubic Yards: The Square Yard Calculator
Concrete is ordered in cubic yards, but plans and flooring are often measured in square yards. A square yard measures area only, so you also need the thickness to find the volume.
Square yards
Square feet ÷ 9 = Square yardsCubic yards
Square yards × Thickness in yards = Cubic yardsThickness in yards = inches ÷ 36
Example: A 144 square foot patio is 144 ÷ 9 = 16 square yards. At 4 inches thick (4 ÷ 36 = 0.111 yards), the volume is 16 × 0.111 = 1.78 cubic yards, which matches the earlier example.
Concrete Footer and Footing Calculator
For a footing, treat the trench as a long rectangular box. Multiply length × width × depth, all in feet, and divide by 27. Use the actual width and depth of the form, and calculate each section separately if the footing changes size.
- Width: 16 ÷ 12 = 1.333 feet; depth: 8 ÷ 12 = 0.667 feet
- Volume: 50 × 1.333 × 0.667 = 44.4 cubic feet
- Cubic yards: 44.4 ÷ 27 = 1.65 cubic yards
- With 10 percent allowance: about 1.81 cubic yards
- In 80 lb bags: 44.4 ÷ 0.6 = about 74 bags (before allowance)
Footings that follow uneven or rough trench walls often use more concrete than the calculation, so a 10 percent allowance is sensible. Local codes set minimum footing sizes, so check requirements for your area.
Round columns and tubes
For a round column or form tube, use the cylinder formula: π × radius² × height, with all measurements in feet. A 12 inch diameter column that is 4 feet tall has a radius of 0.5 feet, so the volume is 3.14 × 0.5 × 0.5 × 4 = 3.14 cubic feet, or about 0.116 cubic yards. That is roughly 5 to 6 bags of 80 lb concrete.
Ready-Mix Concrete or Bagged Concrete?
For small jobs, bagged concrete is convenient. As the volume grows, the number of bags to mix and lift climbs quickly: one cubic yard is about 45 bags of 80 lb concrete, or roughly 3,600 pounds of dry mix. Many DIYers switch to ready-mix delivery once a job reaches somewhere around a cubic yard, though the right point depends on your equipment and helpers.
| Factor | Bagged concrete | Ready-mix delivery |
|---|---|---|
| Best for | Small slabs, post holes, repairs | Patios, driveways, larger slabs and footings |
| Labor | You mix every batch | Truck delivers mixed concrete |
| Timing | Work at your own pace | Placement and finishing must be ready when the truck arrives |
| Quantity | Buy exactly what you need | Ordered in cubic yards, often with minimum or short-load charges |
Concrete Cost: Bagged and Ready-Mix
Prices vary widely by region, mix strength and delivery distance. Many 2026 cost guides put standard ready-mix concrete at roughly $110 to $180 per cubic yard for the material, with delivery fees often adding about $60 to $180 per load. Small orders often cost more per yard because of short-load and minimum charges. Treat these as rough figures and get a local quote.
For bagged concrete, multiply the price per bag by the number of bags. At an example price of $6 per 80 lb bag, one cubic yard (45 bags) would cost about $270. Compare that with a delivered ready-mix quote for the same volume, and include your time and equipment.
Tips for ordering concrete
- Round up to the next quarter or half yard, and add your waste allowance.
- Ask the supplier about minimum loads, short-load fees and how long the truck may wait on site.
- Confirm the strength (psi) and mix needed for your project and climate.
- Make sure forms, subgrade and finishing help are ready before the truck arrives.
- Confirm truck access and where it can park to discharge.
Calculating Paving Sand, Base Rock and Other Materials
The same volume method works for any bulk material: length × width × depth in feet, divided by 27 for cubic yards. This helps if you are working out the materials beneath a slab or paver project.
- Paver sand (1 inch bedding layer): 144 × 0.083 = 12 cubic feet, about 0.44 cubic yards
- Base rock (4 inch layer): 144 × 0.333 = 48 cubic feet, about 1.78 cubic yards
- At roughly 1.3 and 1.4 tons per cubic yard: about 0.6 tons of sand and 2.5 tons of base rock
Base depth depends on the paver system, soil and climate, so follow the manufacturer’s guidance. Estimate it with the Paver Base Calculator, work out gravel quantities with the Gravel Calculator, or convert yards to tons with the Rock Calculator.
Concrete countertops
For a concrete countertop, multiply length × width × thickness (in feet). A countertop 8 ft long, 2 ft wide and 1.5 inches thick is 8 × 2 × 0.125 = 2 cubic feet. Countertop mixes are specialty products with their own yields, so use the manufacturer’s bag yield and add a buffer for waste.
Frequently Asked Questions
How do I estimate concrete yards?
Multiply length × width × thickness in feet to get cubic feet, then divide by 27 to get cubic yards. Add about 5 to 10 percent for waste and uneven ground.
How do you calculate how much concrete you need?
Measure the length, width and thickness of the area, convert thickness from inches to feet, multiply the three numbers, and divide by 27. Then add a waste allowance before you order.
How many 80 lb bags of concrete in a yard?
About 45 bags, since an 80 lb bag typically yields roughly 0.6 cubic feet and a cubic yard is 27 cubic feet.
How many 60 lb bags of concrete in a yard?
About 60 bags, because a 60 lb bag typically yields about 0.45 cubic feet.
How many cubic feet are in an 80 lb bag of concrete?
Roughly 0.6 cubic feet. Check the bag label, because yields vary slightly by brand.
How many 80 lb bags of concrete are on a pallet?
Pallets commonly hold around 40 to 45 bags, with 42 a common count. That is roughly 24 to 27 cubic feet, or about 0.9 to 1 cubic yard. Confirm with the retailer.
How much does one bag of concrete cover?
An 80 lb bag covers roughly 1.8 square feet at 4 inches thick, and a 60 lb bag covers about 1.35 square feet at the same thickness.
How much area does a cubic yard of concrete cover?
About 81 square feet at 4 inches thick, 54 square feet at 6 inches, and 108 square feet at 3 inches. Divide 324 by the thickness in inches for a quick estimate.
How many square yards is a cubic yard?
They measure different things, so there is no direct conversion. Square yards measure area and cubic yards measure volume. Multiply the area in square yards by the thickness in yards to get cubic yards.
How much does a yard of concrete weigh?
About 4,000 pounds for ready-mixed concrete. Plan vehicles and equipment accordingly.
How much extra concrete should I order?
Most people add roughly 5 to 10 percent for uneven subgrade, spillage and form variation. Ask your supplier how much extra they recommend for your project.
Is it cheaper to buy bags or order ready-mix?
For small jobs bags are often more practical, while larger pours usually favor ready-mix. Compare the full delivered ready-mix price, including delivery and short-load fees, against the number of bags multiplied by the bag price.
Final Thoughts
To estimate concrete yards, multiply length × width × thickness in feet and divide by 27, then add 5 to 10 percent for waste. One cubic yard is about 45 bags of 80 lb concrete or 60 bags of 60 lb concrete, and it covers roughly 81 square feet at 4 inches thick.
Before ordering, double-check your measurements, confirm the mix and bag yield with your supplier, and plan the pour so the concrete can be placed and finished on time. For the materials under your slab, start with the ExactYard Gravel Calculator or browse the full ExactYard Calculators directory.
Quick-Estimate Table: Yards at 4 Inches Thick
Use this table for a fast estimate at 4 inches thick. Figures are cubic yards before waste.
| Slab size | Area | Cubic yards |
|---|---|---|
| 10 ft x 10 ft | 100 sq ft | 1.23 yd³ |
| 10 ft x 20 ft | 200 sq ft | 2.47 yd³ |
| 12 ft x 12 ft | 144 sq ft | 1.78 yd³ |
| 20 ft x 20 ft | 400 sq ft | 4.94 yd³ |
| 24 ft x 24 ft | 576 sq ft | 7.11 yd³ |
Rule of thumb: square feet × depth in inches ÷ 324 = cubic yards, then add 10% waste.
For a full calculation, use the Concrete Calculator or the Cubic Yard Calculator.
Related calculators
For bag counts, use the concrete bag calculator.