How Much Concrete Do I Need for a Footing?

Last reviewed: November 18, 2026. Formulas checked against standard industry conversions. How we calculate.

Quick answer: If you are wondering how much concrete do I need for a footing, here it is: for a typical 40 ft long, 12 in wide, 8 in deep strip footing, you need 26.67 cubic feet (0.99 cubic yards) of concrete — buy 29.33 cubic feet (1.09 cubic yards) with a 10% waste allowance. That is 49 bags of 80-lb mix or 66 bags of 60-lb mix, plus 80 ft of rebar (4 x 20-ft bars), for about $162.94 of concrete. Use our Concrete Footing Calculator to work out your exact footing in seconds.

A footing is the wide, flat strip of concrete that spreads the weight of a wall, foundation, or deck across the ground. Getting the volume right matters: order too little and the truck leaves before the pour is finished; order too much and you pay for concrete you cannot use. This guide shows the formula, worked examples from our Concrete Footing Calculator, a bag table by footing size, and how much rebar to buy.

How to calculate concrete for a footing

Multiply the length by the width by the depth, with every dimension in feet, then divide by 27 to convert cubic feet to cubic yards:

Volume (cu ft) = length (ft) x width (ft) x depth (ft)
Volume (cu yd) = volume (cu ft) / 27

Convert inches to feet by dividing by 12. A 12-inch wide footing is 1 foot wide; an 8-inch deep footing is 0.667 feet deep. Then add 10% waste to the exact volume — that is the amount to order or the amount to buy bags for. The Concrete Footing Calculator does all of this for you, including bag counts, rebar, and cost.

Worked examples

Example 1: 40 ft long x 12 in wide x 8 in deep footing

Volume: 40 x 1 x 0.667 = 26.67 cu ft (0.99 cu yd). With 10% waste, buy 29.33 cu ft (1.09 cu yd). Bags: 45 exact / 49 buy 80-lb bags, or 60 exact / 66 buy 60-lb bags. Rebar: two continuous bars give 80 ft of rebar, or 4 x 20-ft bars. Concrete cost: about $162.94.

Example 2: 30 ft long x 16 in wide x 12 in deep footing

Volume: 30 x 1.333 x 1 = 40.00 cu ft (1.48 cu yd). With 10% waste, buy 44.00 cu ft (1.63 cu yd). Bags: 67 exact / 74 buy 80-lb bags, or 89 exact / 98 buy 60-lb bags. Rebar: 60 ft of rebar, or 3 x 20-ft bars. Concrete cost: about $244.44.

Concrete bags for a footing, by size

Bag counts below are per 10 feet of footing, with 10% waste already included. An 80-lb bag yields 0.60 cubic feet and a 60-lb bag yields 0.45 cubic feet.

Footing size (width x depth)Volume per 10 ft (cu ft)Volume per 10 ft (cu yd)80-lb bags to buy60-lb bags to buy
12 in x 8 in6.670.251317
12 in x 12 in10.000.371925
16 in x 8 in8.890.331722
16 in x 12 in13.330.492533
18 in x 12 in15.000.562837
24 in x 12 in20.000.743749

For a footing longer than 10 feet, multiply the bag count by the length in 10-foot sections — or just enter your exact length in the Concrete Footing Calculator. For footings over about 1 cubic yard, ready-mix concrete from a truck is usually cheaper and far less work than mixing bags.

How much rebar does a footing need?

A strip footing normally has two continuous longitudinal rebar bars running its full length. That means the total rebar is twice the footing length: a 40 ft footing needs 80 ft of rebar, and a 30 ft footing needs 60 ft. Rebar is sold in 20-ft bars, so divide the total by 20 and round up — 80 ft is 4 bars, 60 ft is 3 bars. Use our Rebar Calculator if your footing needs a different bar layout, and always check local code for the bar size and cover your footing requires.

How much waste should I add?

Add 10% to the exact volume. It covers spillage, a trench that is wider or deeper than planned in places, and concrete left in the wheelbarrow or mixer. The calculator shows both the exact volume and the volume with waste — order the with-waste amount. On a long footing, even a small over-dig adds up: a 40 ft trench dug half an inch too deep needs about 1.7 extra cubic feet of concrete.

Footing vs deck footings vs Sonotube

A strip footing is one continuous pour under a wall or foundation. A deck footing is different: it is a set of separate, isolated footings, one under each post. Those are usually round piers formed with a Sonotube, or a square column on a pier footing — work those out with our Concrete Column Calculator, which handles round and square columns plus the pier footing underneath. The volume formula is the same idea (cross-section times height), but a strip footing is measured by length, while a pier is measured by the number of posts.

How much does concrete for a footing cost?

At $150 per cubic yard, a 40 ft x 12 in x 8 in footing costs about $162.94 of concrete with waste, and a 30 ft x 16 in x 12 in footing costs about $244.44. Ready-mix is priced per cubic yard, so the with-waste volume is what you pay for. Bags cost more per cubic yard but make sense for small footings: a single 80-lb bag is about $5 to $7 at a home center, so a small 10 ft footing can cost $65 to $90 in bags alone. If your supplier quotes a different price per cubic yard, enter it in the Concrete Footing Calculator to update the cost.

Frequently asked questions

How many cubic yards of concrete do I need for a footing?

Multiply length x width x depth in feet and divide by 27. A 40 ft x 12 in x 8 in footing needs 0.99 cubic yards exactly — order 1.09 cubic yards with 10% waste.

How many bags of concrete for a 40 ft footing?

For a 40 ft long, 12 in wide, 8 in deep footing, buy 49 bags of 80-lb mix or 66 bags of 60-lb mix, including the 10% waste allowance.

How deep should a footing be?

Footings are commonly 8 to 12 inches deep, and they must sit below the local frost line and on undisturbed soil. Check your local building code — frost depth and footing width rules vary by region.

Do I need rebar in a footing?

Usually yes. Two continuous longitudinal bars are standard for a strip footing. A 40 ft footing needs 80 ft of rebar (4 x 20-ft bars); a 30 ft footing needs 60 ft (3 bars).